Contract W9123807C0004
Kiewit Infrastructure West Co. · Department Of Defense · January 8, 2007
Kiewit Infrastructure West Co. was awarded a federal contract by Department Of Defense (Department Of The Army) on January 8, 2007 for $87.23 million of work in highway, street, and bridge construction. Performance is in Folsom, CA. It was awarded under full and open competition. The contract has been modified 84 times since the base award It uses firm fixed-price contract pricing. The most recent modification was on May 11, 2011.
Contract details
- PIID
- W9123807C0004
- Award type
- Definitive Contract
- Pricing
- Firm Fixed Price
- Set-aside
- No Set Aside Used.
- Competition
- Full And Open Competition
- NAICS
- 237310 · Highway, Street, And Bridge Construction
- Product / service
- Construct/Highways-Rds-Sts-Brdgs-Ra
- Place of performance
- Folsom, CA
- First action
- January 8, 2007
- Latest action
- May 11, 2011
Description
THE ABOVE NUMBERED CONTRACT FOR THE FOLSOM BRIDGE PROJECT, FOLSOM, CA IS MODIFIED TO CORRECT AN ADMINISTRATIVE ERROR TO THE FUNDING. THE FUNDING FOR SUB-CLIN 000101 IS INCREASED BY $145,606.73. THE
Modification timeline
-
May 11, 2011Mod P00084THE ABOVE NUMBERED CONTRACT FOR THE FOLSOM BRIDGE PROJECT, FOLSOM, CA IS MODIFIED TO CORRECT AN ADMINISTRATIVE ERROR TO THE FUNDING. THE FUNDING FOR SUB-CLIN 0$145.6K
-
September 30, 2009Mod P00083APPROACH SLAB CONCRETE$24.3K
-
September 30, 2009Mod P00082CABLE RAIL ASSEMBLIES BUY AMERICA ACT$-8.8K
-
September 29, 2009Mod P00081R00067 DIFFERING SITE CONDITION AT SOUND WALL 1$24.5K
-
September 29, 2009Mod P00080REA FOR INSPECTION OF 42 INCH WATER LINE$11.6K
-
September 28, 2009Mod P00078DISPOSE OF CONCRETE FOUND IN ABUTMENT EX$10.2K
-
September 28, 2009Mod P00079REVISED STORM DRAIN IN OLD ARWEC$36.7K
-
September 23, 2009Mod P00077DELAY POUR AT PIER 3 PIER TABLE$8.7K
-
September 23, 2009Mod P00076REPAIR AND REPLACE SOUND WALL 2 CAULKING, ASPHALT, LIGHTING$26.3K
-
June 1, 2009Mod P00073OVERRUN EXCAVATION QUANTITY; PRISSON DRAINAGE; PIER STRUT DESIGN CONFLICT; WSPPP 2007/2008; ADDITIONAL REBAR DESIGN; RIGIT STELL CONDUIT; LIGHT STANDARD AND CON$4.18M
Similar contracts
| Recipient | Agency | Date | Obligated |
|---|---|---|---|
| Columbus Barricades, Inc | Department Of Defense | December 30, 2025 | $162.2K |
| Statewide Stripes, Inc. | Department Of Defense | December 30, 2025 | $994.7K |
| T1-Mw Joint Venture | Department Of Defense | December 29, 2025 | $0 |
| C. Rallo Contracting Co., Inc. | Department Of Defense | December 29, 2025 | $0 |
| Nwf Contractors Inc | Department Of Defense | December 29, 2025 | $57.5K |
| Olgoonik Enterprises, Llc | Department Of Defense | December 29, 2025 | $336.2K |
Top contractors in NAICS 237310
Lifetime obligated dollars across all federal contracts in this NAICS code.
| # | Contractor | Contracts | Obligated |
|---|---|---|---|
| 1 | Southwest Valley Constructors Co | 10 | $2.34B |
| 2 | Bfbc Llc | 9 | $1.84B |
| 3 | Fisher Sand & Gravel Co | 8 | $1.56B |
| 4 | Slsco, Ltd. | 14 | $1.49B |
| 5 | Miscellaneous Foreign Awardees | 1,643 | $1.26B |
| 6 | Granite Construction Company | 206 | $1.02B |
| 7 | H-K Contractors, Inc. | 54 | $618.91M |
| 8 | The Lane Construction Corporation | 198 | $532.57M |
| 9 | Kiewit Infrastructure Co. | 2 | $460.06M |
| 10 | Kiewit Infrastructure West Co. | 8 | $418.37M |
Track this on BesaGov
Get a free weekly email when this changes — new awards, new sub-awards, new opportunities. No login required.
Continue learning
Keep researching
Frequently asked questions
What is contract W9123807C0004?
Contract W9123807C0004 is a federal contract awarded to Kiewit Infrastructure West Co. by Department Of Defense on January 8, 2007 for $87.23 million of work classified under HIGHWAY, STREET, AND BRIDGE CONSTRUCTION. It has been modified 84 times since the base award.
Who won contract W9123807C0004?
Kiewit Infrastructure West Co. won contract W9123807C0004 from Department Of Defense.
How much is contract W9123807C0004 worth?
Contract W9123807C0004 has obligated $87.23 million to date, with a total potential value of $128.11 million if all options are exercised.